City of Tempe

Tempe Wastewater Collection System

Project No. 008 City of Tempe Arizona

Tempe Wastewater Collection System
Plate 01. Tempe Wastewater Collection System — City of Tempe.

Collaborative Project: Partnered with Insituform Technologies on a Design-d-Build project for the City of Tempe. Scope of Work: Managed sewer bypass pumping, sewer point repairs, manhole inserts, reconstructions, and traffic control across multiple city locations. Challenging Bypass Operation: Self-performed a complex sewer bypass at Kyrene & Guadalupe Rd. intersection, a critical area in Tempe. Bypass Specifications: Designed for a flow rate of 10 million gallons per day (MGD) with a suction lift of 22 vertical feet. Technical Expertise: Addressed limited Net Positive Suction Head Available (NPSHA) for the pumps, showcasing advanced engineering capabilities. Key Contributions: Team members were instrumental in the design, calculations, and submittals for the successful 36" Cured-In-Place Pipe (CIPP) installation.

    Project notes

  1. Collaborative Project:
  2. Partnered with Insituform Technologies on a Design-d-Build project for the City of Tempe.
  3. Scope of Work:
  4. Managed sewer bypass pumping, sewer point repairs, manhole inserts, reconstructions, and traffic control across multiple city locations.
  5. Challenging Bypass Operation:
  6. Self-performed a complex sewer bypass at Kyrene & Guadalupe Rd.
  7. intersection, a critical area in Tempe.
  8. Bypass Specifications:
  9. Designed for a flow rate of 10 million gallons per day (MGD) with a suction lift of 22 vertical feet.
  10. Technical Expertise:
  11. Addressed limited Net Positive Suction Head Available (NPSHA) for the pumps, showcasing advanced engineering capabilities.
  12. Key Contributions:
  13. Team members were instrumental in the design, calculations, and submittals for the successful 36" Cured-In-Place Pipe (CIPP) installation.