TFC ROC-330970 CALL (602) 909-6995
// Projects / 007 / forcemain-repair-western-canal
// Project 007

Forcemain Repair — Western Canal

// Client: Town of Gilbert
Forcemain Repair — Western Canal

Emergency Response: Engaged under Town of Gilbert's emergency procurement JOC due to 18" DIP wastewater forcemain failure. Immediate Mobilization: Deployed crews, equipment, and materials within hours, working continuously for 36 hours. Stabilization and Bypass: Stabilized the failure site and implemented a 4,100-foot high-line sewer bypass to prevent overflow at Islands Lift Station. Condition Assessment: Performed condition assessment of the forcemain while bypass was in place. Collaboration: Assisted Town and Hazen Engineering with developing a permanent repair solution. Permanent Solution: Trenching and installing a permanent parallel 18" HDPE forcemain across McQueen Road. Redundancy and Future-proofing: Designed the new setup to handle existing flows and provide future redundancy.

  1. 01 Emergency Response:
  2. 02 Engaged under Town of Gilbert's emergency procurement JOC due to 18" DIP wastewater forcemain failure.
  3. 03 Immediate Mobilization:
  4. 04 Deployed crews, equipment, and materials within hours, working continuously for 36 hours.
  5. 05 Stabilization and Bypass:
  6. 06 Stabilized the failure site and implemented a 4,100-foot high-line sewer bypass to prevent overflow at Islands Lift Station.
  7. 07 Condition Assessment:
  8. 08 Performed condition assessment of the forcemain while bypass was in place.
  9. 09 Collaboration:
  10. 10 Assisted Town and Hazen Engineering with developing a permanent repair solution.
  11. 11 Permanent Solution:
  12. 12 Trenching and installing a permanent parallel 18" HDPE forcemain across McQueen Road.
  13. 13 Redundancy and Future-proofing:
  14. 14 Designed the new setup to handle existing flows and provide future redundancy.