Forcemain Repair — Western Canal
Emergency Response: Engaged under Town of Gilbert's emergency procurement JOC due to 18" DIP wastewater forcemain failure. Immediate Mobilization: Deployed crews, equipment, and materials within hours, working continuously for 36 hours. Stabilization and Bypass: Stabilized the failure site and implemented a 4,100-foot high-line sewer bypass to prevent overflow at Islands Lift Station. Condition Assessment: Performed condition assessment of the forcemain while bypass was in place. Collaboration: Assisted Town and Hazen Engineering with developing a permanent repair solution. Permanent Solution: Trenching and installing a permanent parallel 18" HDPE forcemain across McQueen Road. Redundancy and Future-proofing: Designed the new setup to handle existing flows and provide future redundancy.
- 01 Emergency Response:
- 02 Engaged under Town of Gilbert's emergency procurement JOC due to 18" DIP wastewater forcemain failure.
- 03 Immediate Mobilization:
- 04 Deployed crews, equipment, and materials within hours, working continuously for 36 hours.
- 05 Stabilization and Bypass:
- 06 Stabilized the failure site and implemented a 4,100-foot high-line sewer bypass to prevent overflow at Islands Lift Station.
- 07 Condition Assessment:
- 08 Performed condition assessment of the forcemain while bypass was in place.
- 09 Collaboration:
- 10 Assisted Town and Hazen Engineering with developing a permanent repair solution.
- 11 Permanent Solution:
- 12 Trenching and installing a permanent parallel 18" HDPE forcemain across McQueen Road.
- 13 Redundancy and Future-proofing:
- 14 Designed the new setup to handle existing flows and provide future redundancy.