Hayden 101 Waterline Replacement
Willmeng ConstructionWorking with Willmeng Construction to Install approximately of 2700 LF of 16" DIP from just East of N 73rd Place along the Mayo Blvd alignment East past the Miller Road alignment to replace an existing 16" Steel Cylinder Watermain that conflicts with future de
Project scope
- Working with Willmeng Construction to Install approximately of 2700 LF of 16" DIP from just East of N 73rd Place along the Mayo Blvd alignment East past the Miller Road alignment to replace an existing 16" Steel Cylinder Watermain that conflicts with future developments in its path.
- Project also includes 730 LF of 24" DIP from Mayo Blvd alignment North along the future Miller Road to just South of the 101 and future underpass of Miller Road.
- February 2025 completion of this watermain will allow several developments to move forward without delay.