TFC ROC-330970 CALL (602) 909-6995
// Projects / 009 / peoria-logistics-park
// Project 009

Peoria Logistics Park

// Client: Contracted under GC
Peoria Logistics Park

Subcontracted Project: Worked under a General Contractor for the Peoria Logistics Park, a 158-acre industrial park in southern Peoria, Arizona. Cost: $1.425 million. Market: Site Utilities. Strategic Location: Near Loop 101 and Grand Avenue (US 60), with easy access to major interstates and 6-9 miles from I-10. Site Readiness: Shovel-ready with existing infrastructure and zoning for industrial use, suitable for semiconductor facilities. Scope: Onsite and offsite utility installations and asphalt improvements for a 155,000 SF tilt-up, build-to-suit distribution facility. Utility Infrastructure: Water, sewer, gas, electric, and communication services adjacent to the property, provided by City of Peoria, Southwest Gas, and CenturyLink. Water Line Installation: Installed 5,361 feet of 4", 6", and 8" DIP. Installed 1 16x8" Tapping Sleeve. Installed 9 8" Gate Valves. Installed 13 6" Gate Valves. Installed 4 4" Gate Valves. Installed 12 Fire Hydrants. Completed 5 Vertical Realignments. Installed 1 Blow Off. Installed 1 4" Backflow. Installed 2 Remote FDCs. Sewer Line Installation: Installed 959 feet of 6" and 8" PVC. Installed 3 48" Manholes. Installed 2 6" Cleanouts. Storm Drain Installation: Installed 111 feet of 18" and 24" HDPE. Irrigation Line Installation: Installed 629 feet of 24" RCP. Installed 1 Irrigation Box. Asphalt Replacement: Replaced 794 square yards of asphalt. Reliable Power Supply: SRP operates a major substation and power generation facility across the street, ensuring steady power. Developer Partnership: The VanTrust Group, developer/partner on the site, facilitates build-to-suit/lease-back facilities.

  1. 01 Subcontracted Project:
  2. 02 Worked under a General Contractor for the Peoria Logistics Park, a 158-acre industrial park in southern Peoria, Arizona.
  3. 03 Cost: $1.425 million.
  4. 04 Market:
  5. 05 Site Utilities.
  6. 06 Strategic Location:
  7. 07 Near Loop 101 and Grand Avenue (US 60), with easy access to major interstates and 6-9 miles from I-10.
  8. 08 Site Readiness:
  9. 09 Shovel-ready with existing infrastructure and zoning for industrial use, suitable for semiconductor facilities.
  10. 10 Scope:
  11. 11 Onsite and offsite utility installations and asphalt improvements for a 155,000 SF tilt-up, build-to-suit distribution facility.
  12. 12 Utility Infrastructure:
  13. 13 Water, sewer, gas, electric, and communication services adjacent to the property, provided by City of Peoria, Southwest Gas, and CenturyLink.
  14. 14 Water Line Installation:
  15. 15 Installed 5,361 feet of 4", 6", and 8" DIP.
  16. 16 Installed 1 16x8" Tapping Sleeve.
  17. 17 Installed 9 8" Gate Valves.
  18. 18 Installed 13 6" Gate Valves.
  19. 19 Installed 4 4" Gate Valves.
  20. 20 Installed 12 Fire Hydrants.
  21. 21 Completed 5 Vertical Realignments.
  22. 22 Installed 1 Blow Off.
  23. 23 Installed 1 4" Backflow.
  24. 24 Installed 2 Remote FDCs.
  25. 25 Sewer Line Installation:
  26. 26 Installed 959 feet of 6" and 8" PVC.
  27. 27 Installed 3 48" Manholes.
  28. 28 Installed 2 6" Cleanouts.
  29. 29 Storm Drain Installation:
  30. 30 Installed 111 feet of 18" and 24" HDPE.
  31. 31 Irrigation Line Installation:
  32. 32 Installed 629 feet of 24" RCP.
  33. 33 Installed 1 Irrigation Box.
  34. 34 Asphalt Replacement:
  35. 35 Replaced 794 square yards of asphalt.
  36. 36 Reliable Power Supply:
  37. 37 SRP operates a major substation and power generation facility across the street, ensuring steady power.
  38. 38 Developer Partnership:
  39. 39 The VanTrust Group, developer/partner on the site, facilitates build-to-suit/lease-back facilities.